REPORT ON READINESS TO TACKLE THE Y2K
26 February 1999
CONTENT
Report on Readiness to Tackle the year AD 2000 (Y2K)
Problem
1. Y2K Projects progress 1
1.1 Computer system 1
1.2 MTX / MSC Switching systems 1
1.3 Total cost of investment 1
2. Analysis and explanation of the management 1
2.1 Internal AIS Computer system 1
2.2 External System outside AIS 2
3. Year 2000 Project Implementation 2
3.1 Y2K Problem Solving Phase 2
3.2 Group of persons of agencies responsible
for solving the problem 3
4. Report on the Preparation of ADVANCs
Subsidiary to Cope with 4
the Y2K Problem
1. Main Computer System 4
2. Telephone Exchange Cabinet System 5
3. Electronic System 5
4. Office System 6
5. External Work Unit 6
6. Contingency Plan 6
7. Analysis and Explanation from Management 8
5. Verification Data 9
Advanced Info Service Public Company Limited.
Report on readiness to tackle the year A.D. 2000
(Y2K) Problem
1. Y2K Projects progress
1.1 Computer System
We have started to develop, test and implement our
major systems which are Y2K compliance since 1997. They
are as the list below :
1.1.1 Customer Administration and Billing
Computer Systems (CUBICS)
1.1.2 Back Office System (SAP/P3)
1.1.3 Service Center System
1.1.4 Call Center System
1.1.5 Intranet System
1.1.6 Datawarehousing, Fraud Management and SIS
Systems
1.2 MTX / MSC Switching systems
We completed the inventory and impact analysis phase in Q3 of 1994.
The testing phase has to be enhanced from Q4 of 1998 to Q1 of 1999
(The detail plan will be shown on next page). Currently we are on
the process of software and equipment upgrade at MTX / MSC switching
and base station nationwide. For Integration test with other system,
it will be completed in June 1999
1.3 Total cost of investment
AIS has deployed new services to the customers consecutively through
computer system since 1996. The cost of Y2K project implementation
will be P.Cs BIOS fixing which is approximately 50 million Baht. For
MTX / MSCs switching software and equipment, the upgrade cost are
included in the maintenance contract agreement.
2. Analysis and explanation of the management
AIS is very confident that all core business systems are
Y2K compliance and all AISs business partners are also
investigating to ensure their Y2K compliance status.
2.1 Internal AIS Computer system
2.1.1 AIS core application systems have been developed since 1997 and they
are Y2K compliance. CUBICS is one of these systems used for delivering
services to customer such as billing, registration, collection, credit
control and customer care services.
2.1.2 Workstation P.C. and P.C. application We are on the step of BIOSs
fixing for P.C. and workstations at Shinawatra towers, Maneeya, Univest
Tower, Muangthongthanee, Branches, Outlets, Service centers and AISs
dealers throughout Thailand. This correction will be completed March
1999
2.1.3 MTX / MSC Switching
Software upgrade for MTX / MSC switching has currently been tested,
implemented and the target integration test with Nokia, Ericsson will
be completed in June 1999
2.2 External System outside AIS
AIS has developed Y2Ks Project incorporate with the third parties to
the ensure the completeness of Y2K compliance on which external and
internal data such as CDR (Call Detail Records), Bank transfer data
and the transaction come from other business units.
2.2.1 Telecomz Service Provider in Thailand.
2.2.2 Banking and Financial Services
3. Year 2000 Project Implementation
3.1 Y2K Problem Solving Phase
Year 2000 Project Implementation
Wireless Communications Shinawatra Group
ACTION PLAN 1998 1999
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1)Preliminary Phase x
Year 2000 Education and P.R. (Incorporate x
with SC&C and CA)Set up Year 2000 Wireless x
Committee x
2)Inventory Analysis Phase x
Inventory of All Computer and None x
Computer Equipment x
3)Impact Analysis Phase
Identification of Impact Computer and None x x
Computer Equipment x x
Identification of Impact Program and Data x x
Software and Hardware Upgrade Strategy x
File / Database Conversion Strategy x
4)Correction Phase x x
Hardware and Firmware Upgrade/Replacement x
Software and Operating System Upgrade x
Program and Data Conversion x
File / Database Conversion x
Bridging All x
5)Testing Phase x x x
Unit Testing x
System and Acceptance Testing x
6)Final Implementation Phase x
Implementation of production system changes
Migration to production
3.2 Group of persons of agencies responsible for solving
the problem
Department Name Position
Head of Committee Arpattra Sringkarrinkul Vice President-Operation Support
Service Operation Busaya Sathirapipatkul Wireless Application Manager
Issara Dachakaisaya Wireless System Management
Peerapan Panitchphathom Billing Management Manager
Niwat Chotwongvoranant Collection & Credit Control
Manager
Jirapong Palanusorn Operation Service Manager
Wallop Thamronglak Administration Support Officer
Suphat Tuntiphut New Product Development Manager
Engineering
Chatchai Saksoonthornsiri Eastern Region Engineering
Manager
Nuwat Prasitvoranant Western Region Engineering
Manager
Boonchai Nirathisai Network Information System
Manager
Wannee Sriviset Software Development Manager
Nontharat Thongpompluksa Value Added Service Manager
Prawat Nikanjanakool Act. AVP-Site & Acquisition
To-Un Napaporn GSM Services Manager
Shinawatra Nirat Kanjananakphan Terminal Product Management
Wireless Chawal Ngamwongsakollert Accounting Manager
Marketing Namfon Nutma Sales Officer
Aroonporn Limsakul Marketing Information Manager
Rawat Manyam Marketing Officer
Thawatchai kajornkittisak General Administration Manager
Wireless Jaranya Tungbanjerdsuk Human Resource Manager
Controller Sansanee Kumpalanuwat Accounting Manager
Pensri Ayutaka Administration Manager
Sunitaya Shinawatra Finance Manager
Poonpol Ngendee Legal Manager
Somchai Cherdchupanyachon Accounting Specialist
Peeraya Sangsingkaew Accounting Specialist
Walaiporn kajeenikorn Logistics & Procurement Manager
Shinawatra Paging Thakolrat Kaewkan Operation Director
Weerasak Rumaneeratanakul MIS Division Manager
4. Report on the Preparation of ADVANCs Subsidiary to Cope
with the Y2K Problem
The Implementation Progress to solve the problem for
Shinawatra Paging Company Limited (SPG)
1. Main Computer System (152)
1.1 Paging System
-Network Operating System, File Servers and 152 Applications for both BKK
offices have been upgraded,connected and passed the Y2K test and started
the implementation.
-Paging System (152) for upcountry offices. The subsidiary started
upgrading and installing and expected to finish in March 1999 with the
cost of 1.6 million baht.
1.2 Business Application System (BAS)
-Backup server has been implemented and tested to be Y2K compliance.
-For the production server, the subsidiary will install the patch on the
operating system no later than February 1999. After that all systems will
be Y2K compliance.
1.3 Invoice Printing System
-Laser Printer using Siemen 2090 has no impact from the Y2K problem.
-PC controlling the printing process has no impact from the Y2K problem.
-Envelope Folding Machine has no impact from the Y2K problem.
1.4 Value Added Service
-Stock Alert System has no impact from the Y2K problem.
-The 153 System has no impact from the Y2K problem.
-MoneyLink System has no impact from the Y2K problem.
-Internet Service System has no impact from the Y2K problem.
-Email Alert System has no impact from the Y2K problem.
-CDROM Page System has no impact from the Y2K problem.
-IVR System providing the automatic billing inquiry service has no impact
from the Y2K problem.
1.5 Networks equipment
-Router Equipment. The subsidiary is upgrading the firmware to support Y2K,
to be completed by the middle of March 1999.
-Terminal Server of Annex Terminal Server was changed its firmware.
-Satellite System of Acumen and Samart has no impact from the Y2K problem.
-Ethernet Hub, Switching Hub, LAN Card, Modem and Multiplexer have no
impact from the Y2K problem.
-Optic Mux has no impact from the Y2K problem.
1.6 Paging System
-Glenayre 3000 XL (Version 5.02). The subsidiary has tested and found no
problem.
-Glenayre 3000 Model M, S and ES (Version 5.01) have been tested and
implemented by setting the date backward and found no impact from Y2K.
-C2000 has no impact from the Y2K problem.
2. Telephone Exchange Cabinet System
2.1 PABX Model Definity G3r4 and G3iV3 has no impact from the Y2K problem.
2.2 PABX Model Definity G3rV2 needs to be patched,anticipated to be completely
done by February 1999.
2.3 PABX Model Panasonic KXT-1232 has no impact from the Y2K Problem.
2.4 CMS R3V2 the subsidiary set the date backward and find it works properly.
No impact from the date.
3. Electronic System
3.1 UPS
. -Emerson (Libert) has no impact on the Y2K problem
-Comet (MGE) has no impact on the Y2K problem
-Iwatec (Wartford) has no impact on the Y2K problem
-Leonic (Leonic) has no impact on the Y2K problem
-Powertronic (Shinabis) has no impact on the Y2K problem
-Siemens (Watford) has no impact on the Y2K problem
-Socomec (Unitrio) has no impact on the Y2K problem
3.2 Generator
-Petbow (U-Gen) has no impact on the Y2K problem
-Dale (Dale) has no impact on the Y2K problem
-Thai-Gen (Thai-Gen) has no impact on the Y2K problem
-Onan (Diethelm) has no impact on the Y2K problem
-Cummins (Diethelm) has no impact on the Y2K problem
4. Office System
4.1 Computer
-The survey of the offices hardware discovered that there
are still some hardware which is not compliant to Year
2000, but this problem can be resolved by using with the
software that can help push the hardware running through
Year 2000.
-OS and Software require the version upgrade, being in the
process, and are anticipated to be completely done by
30/04/1999 with the expected cost of 850,000 baht.
4.2 Other office systems do not have the impact form the Y2K problem.
5. External Work Unit
The subsidiary has received the responses back from all related
external work units that they are ready to tackle the Y2K problem.
6. Contingency Plan
The Y2K committee started preparing the contingency plan into 2 parts.
1. Individual Contingency Plan for each system.
2. Contingency Plan for external impact.
More detail will be informed in the next report.
Year 2000 Project Implementation
ACTION PLANS 1998 1999
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1)Preliminary Phase X
Year 2000 Education X
Setup Year 2000 committee X
2)Inventory Analysis Phase X X X
Inventory of all computer and non- X X X
computer equipment
3)Impact Analysis Phase X X
Identification of impact computer and X
equipment
Identification of impact program and data X X
Software and hardware upgrade strategy X X
File/database conversion strategy X
4)Correction Phase X X X
Hardware and firmware upgrade/replacement X X X
Software and operating system upgrade X X X
Program and data conversion X X
File/Database conversion X X
Bridging all X X
5)Testing Phase X X X
Unit Testing X X X
System and acceptance testing X X
6)Final Implementation Phase X X
Implementation of production system change X X
Migration to production X X
7.Analysis and Explanation from Management
The preparation to handle the Y2K problem of the subsidiary is in
the correction phase and testing phase. The progress of the
preparation is more than 80% and will be on schedule to be
completed within Q1 of 1999. The paid expense is 5,860,000
baht and it is expected the further expense of 8 million baht.
Verification of Data
We have already checked all the text and data present in this
report form and hereby certify that they are correct and completed.
No misunderstanding contents as well as the loss of relevant
information that may causes damages to a person holding securities
or making a tender offer, has been found in this report.
For the purpose of authentication that this report is a
certified document set, we have assigned Mrs. Arpattra
Sringkarrinkul to be an authorized person, by affixing his signature
for authentication on each page of this document set. If any
document does not contain the signature of Mrs. Arpattra
Sringkarrinkul , we hereby regard that it is not our certified data.
Name Position
Signature
1. Mr. Paiboon Limpaphayom(Ph.D.) Director
-Signature-
2. Mrs. Boonklee Plangsiri Director
-Signature-
3. Mrs. Somprasong Boonyachai Director
-Signature-
4. Miss Siripen Sitasuwan Director
-Signature-
Authorized Appointee
Mrs. Arpattra Sringkarrinkul Vice President-
Operation Support
-Signature-